 |
This new jetty will be built together with the Port of Rotterdam
* Length: 653 metres * 2 berths for seavessels up to 150.000 dwt (can be used for barges as well) * 2 berths for barges up to 20.000dwt * 4 fuel oil loading arms 12" for seavessels (2 per berth) * 4 fuel oil loading arms 10" for barges (1 per berth) * 1 jet fuel /gasoil loading arm 16" for seavessels * 2 jet fuel loading arms 10" for barges * 1 gasoil loading arm 10" for barges
|
 |
First Sea vessel at new jetty February 2008
|
 |
December 2007 |
 |
October 2007 |
 |
August 2007 |
 |
The jetty from another perspective June 2007 |
 |
View on the jetty April 2007 |
 |
Side view on the jetty 28 March 2007 |
 |
Installation of new loading arms 13 March 2007 |
 |
Side view on the jetty 26 February 2007 |
 |
All fenders and mooring appurtenances installed by Rotterdam Harbour Authorities
25 January 2007 |
 |
Jetty landing: installation of piping in good progress.
30 November 2006
|
 |
Top view of Jetty under construction. Concrete for platform for seagoing vessels (far end) to be pured in the coming weeks.
12 October 2006 |
 |
Hangscaffold was installed under the complete jetty to ensure a safe workarea for piping contractor.
27 September 2006
|
 |
29 August 2006 |
 |
Pouring concrete
31 July 2006 |
 |
Preparations for barge platform
30 June 2006 |
 |
27 April 2006 |
 |
26 April 2006 |
 |
23 March 2006 |
 |
Pile driving for the substructure of jetty
28 February 2006
|
.jpg) |
Pile driving for the substructure of jetty
24 February 2006
|
 |
Preparations for pile driving
7 February 2006
The depth of this area of the Port is such that extra long piles are required for the jetty. The jetty will rest on a total of 186 steel piles (of diameters of as much as nearly 1 m and lengths to almost 50 m). A further 43 steel piles (of diameters to 3m and lengths in excess of 50 m) will be required for the catwalks, fender walls and bollards. |
 |
Preparations quay
31 January 2006 |
 |
Construction site
November 2005 |