planned operational limitations

Please find below all planned operational limitations 

(update 14/03/10 12.00 hrs)

 

Vopak Terminal Europoort

Week 12

 

On Tuesday, March 23rd from 07.00 - 16.00 hrs we have scheduled te remove and re-install a fuel oil pump in phase 5. This imlies that no manipulations can take place during this maintenance.

 

Week 15

On Monday, April 12th from 07.00 until Friday, April 16th 27.00 hrs jety VP3 will be out of order for manintenance. This implies that we cannot berth seagoing vessels at this jetty during the a.m. period.

Week 19

 

On Wednesday, May 12th from 08.00 - 16.00 hrs we have scheduled maintenance for barge jetty T3. This implies that we cannot berth barges at this jetty during the a.m. period.

Week 23

 

On Monday, June 7th from 07.00 until Friday, June 11th 24.00 hrs jety VP1 will be out of order for manintenance. This implies that we cannot berth seagoing vessels at this jetty during the a.m. period.

Week 27

 

On Monday, July 5th from 07.00 until Wednesday, July 7th 23.00 hrs  we have schedued maitenance for barge jetties Tronox.  During this maintenance no barges can berth at these jetties.

Week 29

 

On Wednesday, July 21st from 08.00 - 13.00 hrs we have scheduled maintenance for the valves of all Neckarhaven jetties. During the maintenance we cannot load or dscharge barges at or Neckarhaven jetties. All manipulations will be stopped/interrupted, however
barges can stay at the jetties during the maintenance.

 

Vopak Terminal Laurenshaven

Until furter notice

On December 18th we experienced a mechanical problem with one of the valves at Laurenshaven. For safety reasons we can only handle two manipulations at the same time;

 - 2 x barges, or
- 1x vessel and 1 x barge, or
- 1 pump over between two Laurenshaven tanks (this makes use of two headers, which acts as two manipulations at the same time).

In the near future we will inform you on the remaining maintenance to be performed at Laurenshaven. This, in order to return back to the original situation, where 3 headers should be available and one extra manipulation can be executed at the same time.same time (as we can use two headers);

Congestion may possibly occur at the jetties until this valve has been replaced, as we can still only load/discharge one barge at a time.

 

Vopak Botlek-North Terminal

Week 13

On Monday, March 29th from 07:00 hrs until Friday, April 2nd 2010 untill 17:00 hrs we will be performing maintenance on jetty 5/7. During this time window no barges/vessels can berth alongside Jetty 5/7, however LCO can be loaded / discharged at berth 1/2. 
 

Week 43

Monday, October 25th from 07:00 hrs until Friday, October 29th 2010 untill 17:00 hrs we will be perfoming maintenace on jetty 1/2. During this maintenance window no barges/vessels can berth alongside Jetty 1/2, however LCO and FUEL OIL can be loaded / discharged at erth 5/7 (except for vessels with DWT > 6600 Mton).

 